DevFeeFinder
DrainageSet by special district feeCitation Sacramento County Water Agency Code Title 2 ch. 2.50 (Schedule "A"), ch. 2.75 (Zone 11C sub-fees) and ch. 2.81 (Zone 11N); Fee Plan adopted by Resolution No. WA-3202, 2026-02-10, fee schedule effective 2026-03-02

SCWA Drainage Fee - Zone 11A

Levied by Sacramento County Water Agency on new development in Elk Grove.

What one house pays

$3,302

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot — this fee varies by the row that applies, so see the full schedule below.

Share of Elk Grove's total
4%
Total one-time fees here
$90,015
Adjustment
Adjusts yearly · ENR construction cost index · March
what the document says

annual, Engineering News Record construction cost index, every March 1 or thereabouts

Next expected change
1 Mar 2027

The record

Why it exists

“Development activities, such as grading and paving, significantly increase the imperviousness of land, which in turn increases stormwater runoff volume and flow, impacting water quality. To mitigate these effects, developers and builders are required to pay drainage impact fees (Zone 11 fees) based on the percentage increase in imperviousness created by development. Drainage impact fees are then used to reimburse developers and builders for regionally beneficial drainage improvements.”

Board letter, For the Agenda of: February 10, 2026, "BACKGROUND" · source document ↗
What it pays for

“The Zone 11A, 11B, and 11C Fee Program collects fees and reimburses developers for the construction of large drainage features that drain more than 30 acres. These features include drainage pipes, concrete structures, channel and detention basin excavation, detention basin land, other drainage appurtenances, and review of drainage studies and improvement plans.”

Board letter, February 10, 2026, "BACKGROUND", pp.1-2 · source document ↗
Where it applies

“1. Zone 11 A - Morrison Creek stream group and watersheds draining to the Beach Stone Lake region. 2. Zone 11 B - American River tributaries and Arden/Arcade watersheds. 3. Zone 11 C - Dry Creek and tributaries and watersheds draining to Steelhead Creek (aka. Natomas East Main Drainage Channel). Zones 11A, 11B, and 11C are regional and overlap the political boundaries of the Cities of Citrus Heights, and Elk Grove.”

Zone 11A/11B/11C Fee Plan, 2026-02-10, "Fee Zones", plan pp. 2-3 · source document ↗
When it was adopted

1996 (Zone 11A created; the Zone 11 drainage impact fee program was initiated in 1965)

“WHEREAS, the Sacramento County Water Agency ("Agency") Board of Directors initiated the Zone 11 regional drainage impact fee program in 1965; and WHEREAS, in 1996 the Agency Board of Directors divided Zone 11 into Zones 11A, 11B, and 11C to finance the construction of drainage facilities necessitated by new construction and development; and WHEREAS, the Sacramento County Water Agency Code requires a Fee Plan for each zone, and the Board of Directors adopted a comprehensive Fee Plan for Zones 11A, 11B, and 11C in 1996, and has revised said Fee Plan from time to time”

Resolution No. WA-3202, adopted 10 February 2026, recitals · source document ↗
Who collects it

the Sacramento County Water Agency itself, one budget account per zone

“The fees for each Zone are collected and administered by the Sacramento County Water Agency. Each Zone has a separate budget account, and the funds are not co-mingled.”

Zone 11A/11B/11C Fee Plan, 2026-02-10, "Fee Zones", plan p. 3 · source document ↗
Who is exempt

no fee on open space, creeks, bio-swales or detention basins

“No fee is charged for areas encumbered by open space, creeks, bio-swales and detention basins.”

Zone 11A/11B/11C Fee Plan, 2026-02-10, "Drainage Fee Calculation", plan p. 5 · source document ↗
Credits and offsets

“The overall intention of the trunk drainage fee and credit program is to compensate developers for installing facilities that serve their neighbors. The credits are not intended to fully compensate developers for the drainage facilities presuming that every development would need to establish a drainage system. ... Minor drainage systems serve less than 30-acres of watershed and trunk drainage serves more than 30-acres. This is a bright line, and this program intentionally offers no credits for minor drainage of any sort.”

2026 Fee Plan, "Credits for Construction of Trunk Drainage", p.8 · source document ↗

Every published rate

Land useApplies toBasisEffectiveAmount
Zone 11A
Mobile home (none) per acre — $27,540
the line this rate was read from

“Mobilehome Park | $27,540" under column heading "March 2026 Zone 11A Fee (per acre)”

the levying document · source document ↗
Multi-family RD20 to RD30 per acre — $26,668
the line this rate was read from

“Residential RD20 to RD30 | $26,668" under column heading "March 2026 Zone 11A Fee (per acre)”

the levying document · source document ↗
Single-family detached Residence on 0.10 acres per acre 2 Mar 2026 $25,006
the line this rate was read from

“Residence on 0.10 acres | $25,006 — under the column heading "March 2026 Zone 11A Fee (per acre)" in the table headed "Land Use | March 2026 Zone 11A Fee (per acre) | March 2026 Fee for Parcels Recorded before 8/16/2004 (per acre)"”

Sacramento County Water Agency, Drainage Fee Schedule "A", Fee Schedule Effective March 2, 2026, published as HTML at the Zone 11A/11B/11C rates-and-fees page · source document ↗
Single-family detached Residence on 0.14 acres per acre 2 Mar 2026 $23,016
the line this rate was read from

“Residence on 0.14 acres | $23,016 — under the column heading "March 2026 Zone 11A Fee (per acre)" in the table headed "Land Use | March 2026 Zone 11A Fee (per acre) | March 2026 Fee for Parcels Recorded before 8/16/2004 (per acre)"”

Sacramento County Water Agency, Drainage Fee Schedule "A", Fee Schedule Effective March 2, 2026, published as HTML at the Zone 11A/11B/11C rates-and-fees page · source document ↗
Single-family detached Residence on 0.20 acres per acre 2 Mar 2026 $21,963
the line this rate was read from

“Residence on 0.20 acres | $21,963 — under the column heading "March 2026 Zone 11A Fee (per acre)" in the table headed "Land Use | March 2026 Zone 11A Fee (per acre) | March 2026 Fee for Parcels Recorded before 8/16/2004 (per acre)"”

Sacramento County Water Agency, Drainage Fee Schedule "A", Fee Schedule Effective March 2, 2026, published as HTML at the Zone 11A/11B/11C rates-and-fees page · source document ↗
Single-family detached Residence on 0.25 acres per acre 2 Mar 2026 $21,221
the line this rate was read from

“Residence on 0.25 acres | $21,221 — under the column heading "March 2026 Zone 11A Fee (per acre)" in the table headed "Land Use | March 2026 Zone 11A Fee (per acre) | March 2026 Fee for Parcels Recorded before 8/16/2004 (per acre)"”

Sacramento County Water Agency, Drainage Fee Schedule "A", Fee Schedule Effective March 2, 2026, published as HTML at the Zone 11A/11B/11C rates-and-fees page · source document ↗
Single-family detached Residence on 0.50 acres per acre 2 Mar 2026 $18,702
the line this rate was read from

“Residence on 0.50 acres | $18,702 — under the column heading "March 2026 Zone 11A Fee (per acre)" in the table headed "Land Use | March 2026 Zone 11A Fee (per acre) | March 2026 Fee for Parcels Recorded before 8/16/2004 (per acre)"”

Sacramento County Water Agency, Drainage Fee Schedule "A", Fee Schedule Effective March 2, 2026, published as HTML at the Zone 11A/11B/11C rates-and-fees page · source document ↗
Single-family detached Residence on 1.0 acres per acre 2 Mar 2026 $18,161
the line this rate was read from

“Residence on 1.0 acres | $18,161 — under the column heading "March 2026 Zone 11A Fee (per acre)" in the table headed "Land Use | March 2026 Zone 11A Fee (per acre) | March 2026 Fee for Parcels Recorded before 8/16/2004 (per acre)"”

Sacramento County Water Agency, Drainage Fee Schedule "A", Fee Schedule Effective March 2, 2026, published as HTML at the Zone 11A/11B/11C rates-and-fees page · source document ↗
Single-family detached Residence on 2.0 acres per acre 2 Mar 2026 $13,640
the line this rate was read from

“Residence on 2.0 acres | $13,640 — under the column heading "March 2026 Zone 11A Fee (per acre)" in the table headed "Land Use | March 2026 Zone 11A Fee (per acre) | March 2026 Fee for Parcels Recorded before 8/16/2004 (per acre)"”

Sacramento County Water Agency, Drainage Fee Schedule "A", Fee Schedule Effective March 2, 2026, published as HTML at the Zone 11A/11B/11C rates-and-fees page · source document ↗
Single-family detached Residence on 3.5 acres per acre 2 Mar 2026 $6,839
the line this rate was read from

“Residence on 3.5 acres | $6,839 — under the column heading "March 2026 Zone 11A Fee (per acre)" in the table headed "Land Use | March 2026 Zone 11A Fee (per acre) | March 2026 Fee for Parcels Recorded before 8/16/2004 (per acre)"”

Sacramento County Water Agency, Drainage Fee Schedule "A", Fee Schedule Effective March 2, 2026, published as HTML at the Zone 11A/11B/11C rates-and-fees page · source document ↗
Single-family detached Residence on 5.0 acres per acre 2 Mar 2026 $0.00
the line this rate was read from

“Residence on 5.0 acres | $0 — under the column heading "March 2026 Zone 11A Fee (per acre)" in the table headed "Land Use | March 2026 Zone 11A Fee (per acre) | March 2026 Fee for Parcels Recorded before 8/16/2004 (per acre)"”

Sacramento County Water Agency, Drainage Fee Schedule "A", Fee Schedule Effective March 2, 2026, published as HTML at the Zone 11A/11B/11C rates-and-fees page · source document ↗
—
Single-family detached Beach Stone Lake Volume Mitigation Fee (Zone 11X), flat for any lot of 0.20 acre or smaller per acre 2 Mar 2026 $392.00
the line this rate was read from

“Raw Land and Open Space $0 | Road Right-of-Way, greater than 40' [1] $0 | Residence on 5.0 acres $0 | Residence on 3.5 acres $21 | Residence on 2.0 acres $38 | Residence on 1.0 acres $78 | Residence on 0.50 acres $158 | Residence on 0.25 acres $314 | Residence on 0.20 acres $392 | Residence on 0.14 acres $392 | Residence on 0.10 acres $392 | Residential RD20 to RD30 $392 | Mobilehome Park $392 — the complete third money column of the Zone 11A table, headed "March 2026 Beach Stone Lake (per acre)", with footnote [3] "Beach Stone Lake Volume Mitigation Fee is accounted for separate from Zone 11A."”

Sacramento County Water Agency, Drainage Fee Schedule "A", Fee Schedule Effective March 2, 2026, Zone 11A table, third money column · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.