The record
“Domestic Water System Facilities Financial Participation Charge ('Capacity Charges'/'Connecting Fees') is to provide a source of funds to finance: (1) water main facilities larger than 12-inches in diameter; (2) booster pumping plants; (3) storage tanks; and (4) Improvement District and General District system facilities, as necessary to meet the additional service requirements necessitated by community growth and to distribute the costs fairly among those who create the need for additional facilities.”
“FPCs, sometimes referred to as 'connection fees,' are collected to pay for planned and existing water and wastewater facilities. … Some capital facilities include: o Pipelines o Pumping Stations o Wastewater Treatment Plants o Sewage Transmission Lines o Freshwater Connections o Sewage Lift Stations”
“APPENDIX A: WATER SERVICE AREA AND IMPROVEMENT DISTRICT RATE REFERENCE … SA 42 Hemet San Jacinto … A201 … 1, 4, 5, 12, 42, U-7 (57), U-17 (67), U-20 (70)" and "APPENDIX B: SEWER SERVICE AREA AND IMPROVEMENT DISTRICT RATE REFERENCE … SA 31 Hemet, San Jacinto … S101 … 17, 20, U-7 (57), U-12 (62), U-14 (64), U-16 (66), U-18 (68), U-19 (69), U-21 (71) … Applicable for sewage collection, transmission, treatment and disposal service rendered through EMWD facilities when no other agency/assignee provides sewage collection.”
“All properties, improved with an existing structure, located within an operating District improvement district providing retail domestic water service prior to the effective date of Resolution 1639 (March 14, 1979), shall be exempt from paying Capacity Charges.”
“All properties, improved with an existing structure, located within an operating District improvement district providing retail domestic water service prior to the effective date of Resolution 1639 (March 14, 1979), shall be exempt from paying Capacity Charges.”
“Payment of Capacity Charges as a Prerequisite to Receiving Service … New developments and non-exempt existing developments requesting retail domestic water service will be required to pay nonreimbursable Capacity Charges (also known as Financial Participation Charges) shown on the Application for Service. In cases where District's Financial Participation Charges had increased subsequent to the issuance of the Application for Service, the District will honor charges quoted on the Application for Service, provided Applicant/Sponsor has executed and fulfilled the Financial Arrangements on or before the date set forth on such Application for Service.”
Eastern Municipal Water District, the agency that levies it
“I pay my sewer bill to someone other than EMWD. Why do I still pay FPCs to EMWD? In some cases, cities or local water agencies construct and operate their own water and sewer facilities that connect with EMWD's facilities. In those instances, you pay for the use of both the city's and EMWD's facilities. If you have questions about other agencies' fees, you must contact them directly.”
“Development to be exempted from Payment of Connection fees: (1) Existing Development Within Improvement Districts … (2) Existing Development Outside of Improvement Districts Receiving Domestic Water Service … (3) Agricultural Use, as defined by the Metropolitan Water District of Southern California Administrative Code … shall be exempt from paying Capacity Charges. (4) New Recycled water meters, including those that are supplied with potable water sources on an interim basis, shall be exempt from paying capacity charges. (5) ADUs converted from existing space and JADU's shall not be considered to be a new residential use and shall be exempt from connection fees or capacity charges.”
“Developer Donated Storage Credit … ($1,247/EMS) [1/1/2025] … ($1,287/EMS) [1/1/2026]”
“Sewer Financial Participation Charge … Area / Rate as of 1/1/2025 / Rate as of 1/1/2026 / Rate as of 6/17/2026 … General District $3,514/EDU $3,626/EDU $3,626/EDU … Murrieta Relief Area Sewer (MARS) Area B & Physicians Hospital of Murrieta $6,940/EDU $7,161/EDU $8,404/EDU”
Every published rate
Every rate below applies to single-family detached.
| Component | Basis | Effective | Amount |
|---|---|---|---|
| Water Financial Participation Charge | per EDU | 1 Jan 2026 | $7,738 |
| Sewer Treatment Plant Capacity Charge | per EDU | 1 Jan 2026 | $6,876 |
| Sewer Financial Participation Charge | per EDU | 1 Jan 2026 | $3,626 |
| Recycled Water Supply Development Fee | per EDU | 1 Jan 2026 | $420.00 |
| Meter install 5/8-3/4 inch (drop-in) | per EDU | 1 Jan 2026 | $285.00 |