Public Facilities Impact Fee - Sheriff Patrol & Investigation

Charged on new development in Kern County (unincorporated). Authorized under the Mitigation Fee Act - Gov. Code Sec. 66000 et seq. Collected other: not stated for this fee; the study states generally that "Public facilities fees are one-time fees typically paid when a building permit is issued".

What one house pays

$432

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot — this fee varies by zone, so see the full schedule below.

Share of Kern County (unincorporated)'s total
1%
Total one-time fees here
$31,204
Adjustment
Adjusts another named index
what the document says

recommended only — the study says the County "should" adjust for inflation "periodically"; it names no index, no date and no mechanism, and it is not an adopting instrument

The record

Why it exists

“The purpose of this fee is to ensure that new development funds its fair share of Sheriff patrol and investigation facilities. The fee will be charged to residential and nonresidential development in unincorporated areas of the County.”

Kern County Public Facilities Impact Fee Study, DRAFT, May 18, 2009, ch. 4 "Sheriff Patrol and Investigation", opening paragraph, report p. 25 · source document ↗
What it pays for

“The County will use fee revenues to expand Sheriff patrol and investigation facilities, including new Sheriff substations and equipment, to serve new development.”

Kern County Public Facilities Impact Fee Study, DRAFT, May 18, 2009, ch. 4, report p. 25 · source document ↗
Where it applies

“The Kern County Sheriff's Department provides basic law enforcement services in the unincorporated area, while City police departments provide law enforcement in incorporated cities. Therefore, the impact fee for Sheriff patrol and investigation facilities will be charged only in unincorporated areas of the County.”

Kern County Public Facilities Impact Fee Study, DRAFT, May 18, 2009, ch. 4 "Service Population", report p. 25 · source document ↗
When it is paid

“Public facilities fees are one-time fees typically paid when a building permit is issued and imposed on development projects by local agencies responsible for regulating land use (cities and counties).”

Kern County Public Facilities Impact Fee Study, DRAFT, May 18, 2009, ch. 13 "Mitigation Fee Act Findings", opening sentence, report p. 102 · source document ↗
How it changes

“Impact fee program adoption procedures are found in the California Government Code section 66016. Adoption of an impact fee program requires the Board of Supervisors to follow certain procedures including holding a public meeting. Data, such as an impact fee report, must be made available at least 10 days prior to the public meeting. The County's legal counsel should be consulted for any other procedural requirements as well as advice regarding adoption of an enabling ordinance and/or a resolution. After adoption there is a mandatory 60-day waiting period before the fees go into effect.”

Kern County Public Facilities Impact Fee Study, DRAFT, May 18, 2009, ch. 12 "Implementation" / "Impact Fee Program Adoption Process", report p. 100 · source document ↗

Every published rate

Land useApplies toBasisEffectiveAmount
Mountain Zone
Multi-family none per DU — $764.81
the line this rate was read from

“Table 4.7: Countywide Sheriff Patrol and Investigation Facility Impact Fees — Mountain Zone / Residential / Multi-family Unit: Cost per Capita 366 | Density 2.08 | Base Fee 761 | Admin. Charge 3.81 | Fee 764.81”

the levying document · source document ↗
Valley Zone
Multi-family none per DU — $615.06
the line this rate was read from

“Table 4.7: Countywide Sheriff Patrol and Investigation Facility Impact Fees — Valley Zone / Residential / Multi-family Unit: Cost per Capita 294 | Density 2.08 | Base Fee 612 | Admin. Charge 3.06 | Fee 615.06”

the levying document · source document ↗
Desert Zone
Single-family detached this homeunverified per DU 1 Jan 2008 $432.15

“Table 4.7: Countywide Sheriff Patrol and Investigation Facility Impact Fees — column headings: A Cost per Capita(1) | B Density(2) | C=AxB Base Fee(3) | D=0.5%xC Admin. Charge(4) | E=C+D Fee. Row: Desert Zone / Residential / Single Family Unit: $ 137 | 3.14 | $ 430 | $ 2.15 | $ 432.15. Footnote 2: 'Persons per dwelling unit or workers per 1,000 square feet.' Footnote 3: 'Fee per dwelling unit (residential) or per 1,000 square feet (nonresidential).' Footnote 4: 'Administrative charge of 0.5 percent to cover costs including fee collection, accounting, annual reporting, and facilities planning.'”

Kern County Public Facilities Impact Fee Study, DRAFT, May 18, 2009, Table 4.7, report p. 34 · source document ↗
Multi-family none per DU — $286.43
the line this rate was read from

“Table 4.7: Countywide Sheriff Patrol and Investigation Facility Impact Fees — Desert Zone / Residential / Multi-family Unit: Cost per Capita 137 | Density 2.08 | Base Fee 285 | Admin. Charge 1.43 | Fee 286.43”

the levying document · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close