Sewer - treatmentSet by special district fee

Cucamonga Valley WD sewer system capacity fee

Levied by Cucamonga Valley Water District (sewer system capacity fee, CVWD Code s.5.08.050); Inland Empire Utilities Agency (Capital Capacity Reimbursement Payment, IEUA Ordinance No. 114 / Regional Sewage Service Contract s.9.E.2) on new development in San Bernardino County (unincorporated). Collected other: prior to release of signed approved plans and start of construction of water and/or sewer facilities.

What one house pays

$1,239

This fee is not in San Bernardino County (unincorporated)'s published figure. This site publishes a home outside any plan area, and this charge applies only in Cucamonga Valley (Cucamonga Valley Water District). The amount shown is what it costs a house that is there.

Total one-time fees here
$41,274
Adjustment
Adjusts only when the board sets a new amount
what the document says

by resolution — stepped amounts fixed by IEUA Board resolution, no index named

The record

Why it exists

“As a condition to sewage treatment service and for the purpose of providing Supplemental Capital Outlay Funds to IEUA, each SCA shall establish and maintain a Capital Capacity Reimbursement Account to which the SCA shall deposit or credit its Capital Capacity Reimbursement Payments.”

Ordinance No. 114, 2023-12-20, Section 9.C.1 General, p. 10 of 31 · source document ↗
What it pays for

“All amounts received by IEUA from the SCAs as Supplemental Capital Outlay Funds shall be deposited in or credited to the Regional Wastewater Capital Improvement Fund. All such amounts together with all interest earned thereon shall be available and utilized by IEUA solely for the purpose of financing the acquisition, improvement and expansion of the Regional Sewerage System.”

Ordinance No. 114, 2023-12-20, Section 9.E Supplemental Capital Outlay Fund Payments, pp. 13-14 of 31 · source document ↗
Where it applies

“Cucamonga Valley Water District / District Boundary" with legend "CVWD Service Boundary", "(83.84%) City of Rancho Cucamonga (25,165 Acres) / (5.54%) City of Fontana (1,663 Acres) / (4.43%) City of Ontario (1,329 Acres) / (0.14%) City of Upland (42 Acres) / (6.05%) Rancho Cucamonga S. O. I. (1,817 Acres)" and "Total Service Area = 30,016 Acres or 47 Square Miles ±"; the map also labels "Unincorporated Area of San Bernardino County / City of Rancho Cucamonga Sphere of Influence”

CVWD District Boundary map, "Updated: 10/12/2018", title block and legend · source document ↗
When it was adopted

2023-12-20 (IEUA regional half only; CVWD's own s.5.08.050 adoption NOT FOUND)

“ADOPTED, this 20th day of December, 2023." and "Upon the effective date of this Ordinance No. 114, Ordinance No. 111, including any amendments thereto, shall be repealed and superseded by this Ordinance. ... This Ordinance shall take effect on January 2, 2024.”

IEUA Regional Sewage Service Ordinance No. 114, adopted 2023-12-20, Section 28 - Effective Date, p. 30 of 31 · source document ↗
Who adopted it

Ordinance No. 114 (Inland Empire Utilities Agency, Regional Sewage Service Ordinance)

“ADOPTED, this 20th day of December, 2023." and "Upon the effective date of this Ordinance No. 114, Ordinance No. 111, including any amendments thereto, shall be repealed and superseded by this Ordinance. ... This Ordinance shall take effect on January 2, 2024.”

IEUA Regional Sewage Service Ordinance No. 114, adopted 2023-12-20, Section 28 - Effective Date, p. 30 of 31 · source document ↗
When it is paid

other: prior to release of signed approved plans and start of construction of water and/or sewer facilities

“For all Development projects, the following fees must be paid prior to release of signed approved plans and start of construction of any water and/or sewer facilities. These fees shall include the following: ... Sewer System Capacity Fees, Capital Capacity Reimbursement Fees. (For Commercial Projects these fees are paid during the Tenant Improvement Plan Check process)”

CVWD Development Fee Schedule, Rev July 2026, item 2, p. 1 of 8 · source document ↗
Who collects it

Cucamonga Valley Water District, as the Sewage Collection Agency, for both charges

“A Capital Capacity Reimbursement Payment shall be deposited or credited to a SCA's Capital Capacity Reimbursement Account for such a new connection or change of use at the time of the issuance of a building permit or a sewer connection permit”

Ordinance No. 114, 2023-12-20, Section 9.C.2.c, p. 11 of 31 · source document ↗
Who is exempt

“Residential Dwellings constructed prior to 1979, are excluded from the Capital Capacity Reimbursement Fee.”

CVWD Development Fee Schedule, Rev July 2026, "Capital Capacity Reimbursement Fees: CVWD Code s.5.08.060", p. 6 of 8 · source document ↗
Credits and offsets

“Notwithstanding the preceding provisions, the amount which a SCA is required to have deposited in or credited to its Capital Capacity Reimbursement account for any such new connection or change of use shall be reduced by payments, if any, made by the SCA to IEUA for the new connection or change of use to support Supplemental Capital Outlay Payments, made at IEUA's request.”

Ordinance No. 114, 2023-12-20, Section 9.C.2.b, p. 11 of 31 · source document ↗
How it changes

“Capital Capacity Reimbursement Fee, per EDU / CVWD Code §5.08.060(A)" over the table "Effective 7/1/2022 | Effective 7/1/2023 | Effective 7/1/2024" / "$7,600 | $8,132 | $8,620”

CVWD Guidelines for New Development Fee Schedule, Rev July 2023, p. 8 of 10 · source document ↗

Every published rate

Land useApplies toBasisEffectiveAmount
none
Multi-family none per EDU — $8,620
the line this rate was read from

“Capital Capacity Reimbursement Fee, per EDU / CVWD Code §5.08.060(A) — $8,620 per EDU ... (A) Residential Projects: EDU determinations for Residential Projects shall be as follows: Single Family ... 1 EDU per dwelling unit; Multiple Family ... 1 EDU per dwelling unit”

the levying document · source document ↗
Mobile home none per EDU — $8,620
the line this rate was read from

“Mobile Home Space ....................... 1 EDU per dwelling unit. Each Single Family, Multiple Family, and Mobile Home Space shall be assessed Capital Capacity Reimbursement Fees of one (1) EDU per dwelling unit.”

the levying document · source document ↗
—
Single-family detached unverified per DU — $1,239
the line this rate was read from

“Sewer System Capacity Fees: (CVWD Code §5.08.050) — (A) Residential: $1,239 per Dwelling Unit”

CVWD Development Fee Schedule, Rev July 2026, section "Sewer System Capacity Fees", p. 5 of 8 · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.