DevFeeFinder
WaterSet by special district feeCitation VCMWD Administrative Code, Article 160

Valley Center MWD water capacity charge

Levied by Valley Center Municipal Water District (the "*VCMWD Meter Capacity" line) and the San Diego County Water Authority (the two "**SDCWA" lines, collected and remitted by VCMWD) on new development in San Diego County (unincorporated). Collected other: in full before the service connection is made — payment of all meter connection costs is part of the water service application, and no meter is processed for installation until the current fees are paid.

What one house pays

$6,943

This fee is not in San Diego County (unincorporated)'s published figure. This site publishes a home outside any plan area, and this charge applies only in Valley Center Municipal Water District. The amount shown is what it costs a house that is there.

Total one-time fees here
$68,467
Adjustment
Adjusts only when the board sets a new amount
what the document says

annual, by ordinance of the Board of Directors on an updated asset valuation — no index is named for the meter capacity charge

Next expected change
1 Jul 2027

The record

Why it exists

“Valley Center Municipal Water District (VCMWD) Meter Capacity Charge. In addition to any other charge provided herein, the applicant requesting new service for any parcel shall be required to pay a VCMWD meter capacity charge for capital improvements to the District's water system”

Administrative Code Article 160, Water Service – Rules and Regulations, Sec. 160.4(c), per Ordinance No. 2026-11 adopted 08/03/26, effective 09/04/26 · source document ↗
What it pays for

“Water Meter Capacity and Annexation Charges will be used for the purpose of financing public facilities as specified in the Memorandum.”

Ordinance No. 2026-11, 2026-08-03, ordaining clause paragraph 3 · source document ↗
Where it applies

“In accordance with the District's Administrative Code Article 160 'Water Service - Rules and Regulations,' a Water Meter Capacity Charge shall be imposed on: a. any parcel without a meter requesting new service; and b. any parcel with an existing meter requesting additional capacity.”

Ordinance No. 2026-11, 2026-08-03, ordaining clause paragraph 5 · source document ↗
When it was adopted

2026-08-03 (current amounts; effective 2026-09-04)

“ORDINANCE NO. 2026-11 / ORDINANCE OF THE BOARD OF DIRECTORS OF VALLEY CENTER MUNICIPAL WATER DISTRICT AMENDING ADMINISTRATIVE CODE ARTICLE 160 INCREASING WATER METER CAPACITY CHARGES AND ARTICLE 220 INCREASING THE ANNEXATION CHARGE ... PASSED AND ADOPTED at a regular meeting of the Board of Directors of the Valley Center Municipal Water District held on the 3rd day of August, 2026”

Attachment 1, Ordinance No. 2026-11, Board Packet for Regular Meeting of August 3, 2026, caption and execution clause · source document ↗
Who adopted it

Ordinance No. 2026-11

“ORDINANCE NO. 2026-11 / ORDINANCE OF THE BOARD OF DIRECTORS OF VALLEY CENTER MUNICIPAL WATER DISTRICT AMENDING ADMINISTRATIVE CODE ARTICLE 160 INCREASING WATER METER CAPACITY CHARGES AND ARTICLE 220 INCREASING THE ANNEXATION CHARGE ... PASSED AND ADOPTED at a regular meeting of the Board of Directors of the Valley Center Municipal Water District held on the 3rd day of August, 2026”

Attachment 1, Ordinance No. 2026-11, Board Packet for Regular Meeting of August 3, 2026, caption and execution clause · source document ↗
When it is paid

“Connection of Service. The applicant shall be required to pay connection, equipment and capacity fees in full before a service connection will be made.”

Administrative Code Article 160, Sec. 160.4, opening paragraph · source document ↗
Who collects it

Valley Center Municipal Water District — same agency collects all three components

“San Diego County Water Authority (SDCWA) Meter Capacity Charge. As required by Section 5.9 of the County Water Authority Act, the District, as a member agency of the San Diego County Water Authority (SDCWA), shall collect and remit to SDCWA the SDCWA meter capacity charge. ... The District shall not provide a water meter to a water user until the water user has paid to the District the applicable SDCWA meter capacity charge.”

Administrative Code Article 160, Sec. 160.4(d), per Ordinance No. 2014-03 adopted 6/2/14 · source document ↗
Who is exempt

“The following are exceptions to this Sec. 160.4: ... 2. No VCMWD meter capacity charge shall be made for relocating meters of equal size whether or not any VCMWD meter capacity charge was in effect when original meter was obtained. 3. No VCMWD meter capacity charge shall be imposed for a water meter obtained and used solely for fire protection purposes.”

Administrative Code Article 160, Sec. 160.4(c), exceptions 2 and 3 · source document ↗
Credits and offsets

“VCMWD Meter Capacity Credits. When an existing meter is downsized in accordance with Section 160.7 hereof, and a credit balance remains, a VCMWD Meter Capacity Credit, in the form of an agreement between the District and property owner, may be issued for the amount of capacity represented by the credit balance ... 8. The capacity credit expires ten (10) years from the date of issuance. ... 11. When used to purchase new meter capacity, the amount of the capacity credit would be multiplied by the 3/4" VCMWD meter capacity charge in place at that time. The capacity credit may be applied only to the VCMWD meter capacity charge and to no other charges.”

Administrative Code Article 160, Sec. 160.4(e), as amended by Ordinance No. 2026-11 adopted 8/3/2026, effective 09/04/2026 · source document ↗

Every published rate

Every rate below applies to single-family detached.

ComponentBasisEffectiveAmount
3/4 inch meter, VCMWD capacity per meter 4 Sep 2026 $6,943
the line this rate was read from

“CAPACITY CHARGES | 3/4" | *VCMWD Meter Capacity | $6,943.00 [footnote] *Valley Center Municipal Water District”

"Water & Wastewater Connection Charges effective 9/4/2026", CAPACITY CHARGES table, row "*VCMWD Meter Capacity", column headed 3/4" · source document ↗

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.

↑↓ navigate↵ openesc close