$54,920

One-time fees on a typical new single-family home: 2,000 sq ft, 0.13 acre lot, three bedrooms, in a new subdivision.

School district: Lodi USD

Source: Development Fee Index, via DevFeeFinder · as of 25 Sep 2026 · Methodology

CountySan Joaquin
School districtLodi USD
Home2,000 sq ft · 0.13 acre
Figures as of25 Sep 2026

Ranked #36 of 61 · Compare all

Fees by category click a slice

Transportation — $17,756 Water — $8,019 Parks — $3,279 Schools — $10,340 Drainage & flood — $4,587 Public safety — $5,195 Other — $5,745
$54,920
16 fees
advertisement

Every fee, and when it is due

FeeCategoryHow it’s chargedDueAmount
Public Facility Fee (PFF) - streets, signals and street treesTransportation2 parts, added togetherBuilding permit$13,336
School Facilities Fee (Level 1) - Lodi USDSchools$5.17 per sq ftBuilding permit$10,340
Delta Water Supply Project (DWSP) Surface Water Supply FeeWaterper water meterNot yet recorded$5,754
PFF - Surface WaterDrainage & floodper homeBuilding permit$4,587
SJCOG Regional Transportation Impact Fee (RTIF)SJCOGTransportation$2.21 per sq ftNot yet recorded$4,420
San Joaquin County Facilities Fee (CFF)SJ CountyPublic safetyper homeNot yet recorded$3,823
PFF - ParklandParksper homeBuilding permit$2,798
SJMSCP habitat mitigation feeAgriculturalSJCOGOther$17,868 per acreBuilding permit$2,323
Municipal Utilities water connectionWaterper water meterBuilding permit$2,264
PFF - Agriculture Land MitigationOther$14,352 per acreMap approval$1,866
PFF - LibrariesOtherper homeBuilding permit$902
PFF - Fire StationPublic safetyper homeBuilding permit$781
PFF - PolicePublic safetyper homeBuilding permit$591
PFF - Community Recreation CenterParksper homeBuilding permit$481
PFF - City Office SpaceOtherper homeBuilding permit$467
PFF - Air QualityOtherper homeBuilding permit$187
Development fees per home · 2,000 sq ft, 0.13 acre lot$54,920

Each line is the one rate this home pays. Most fees publish several rates — by house size, lot, or location — and only one applies. Click a fee for its full schedule and source documents.

Published rates that could not be converted

These are real charges. They are left out of the figure because they cannot be worked out per house without knowing something this site does not assume — a percentage of another fee, a per-room count, a per-application charge.

PFF administrative feepercentrate only
Public Facility Fee (PFF) - streets, signals and street treesper treerate only

Charges that are not part of the one-time total above: fees set as a percentage of another fee, and payments a builder can make instead of building something. Neither is added to the headline figure, because neither is a fixed amount every new home owes.

Percentage surcharges

Administration charges set as a percentage of other fees. Shown as a rate, because what they come to depends on the project.

PFF administrative feeof sum of all Public Facility Fees — about $1,922 on this figure3.5%

Housing and in-lieu options

No housing or inclusionary charge is recorded for Stockton.