DevFeeFinder
WaterSet by connection charge

EMWD Water Financial Participation and Recycled Water Supply Development Charges

Levied by Eastern Municipal Water District on new development in Riverside County (unincorporated). Authorized under the Gov. Code Sec. 66013 (capacity charge for water or sewer service). Collected other: prior to District acceptance of the facilities and provision of service to the unit.

What one house pays

$8,158

For a typical home: a 2,000 sq ft detached house on a 0.13 acre lot, on a new subdivision lot.

Share of Riverside County (unincorporated)'s total
10%
Total one-time fees here
$83,961
Adjustment
Not recorded

The record

Why it exists

“FPCs help ensure that everyone pays a fair share of EMWD's capital facilities. FPCs, sometimes referred to as "connection fees," are collected to pay for planned and existing water and wastewater facilities. Individuals are required to buy in to these capital facilities.”

Eastern Municipal Water District, "FAQ: Financial Participation Charges and Water Supply Development Fee", 1/2026 · source document ↗
What it pays for

“Some capital facilities include: Pipelines; Pumping Stations; Wastewater Treatment Plants; Sewage Transmission Lines; Freshwater Connections; Sewage Lift Stations”

FAQs, 1/2026, "What are Financial Participation Charges (FPCs)?" · source document ↗
Where it applies

“Are FPCs the same throughout EMWD's service area? Yes, in most cases, but not all. Customized FPCs have been set in a few areas where EMWD's costs to provide service have differed from standard cost allocations. Customized fees can be higher or lower than the standard, depending on actual, documented construction costs.”

FAQs, 1/2026 · source document ↗
Who adopted it

Ordinance No. 2025-014

“CURRENT ORDINANCES & RESOLUTIONS ADOPTING CERTAIN RATES, FEES, AND CHARGES … Ordinance 2025-014, Revising Certain Financial Participation Charges, Fees-for-Service, and Water Rate Schedules”

EMWD Consolidated Schedule of Rates, Fees, and Charges, updated 7/15/2026, p. 69 · source document ↗
When it is paid

other: prior to District acceptance of the facilities and provision of service to the unit

“The sponsor/developer must agree to pay the full adjusted amount of such charges prior to District's acceptance of the facilities and provision of service to the involved unit(s).”

Eastern Municipal Water District, "Adopted Consolidated Schedule of Rates, Fees, and Charges", effective January 1, 2025, page footer "Updated 7/15/2026" · source document ↗
Who collects it

Eastern Municipal Water District, the agency that levies it

“Capacity Charges shall be based upon the Consolidated Schedule of Rates, Fees and Charges as established and adjusted by Board Resolution.”

§5.307(c), p. 327 · source document ↗
Who is exempt

“(g) Development to be exempted from Payment of Connection fees: (1) Existing Development Within Improvement Districts: All properties, improved with an existing structure, located within an operating District improvement district providing retail domestic water service prior to the effective date of Resolution 1639 (March 14, 1979), shall be exempt from paying Capacity Charges… (2) Existing Development Outside of Improvement Districts Receiving Domestic Water Service: All properties upon which a completed structure existed prior to the effective date of Resolution No. 1639 (March 14, 1979), which were located outside an operating District improvement district but being provided with retail domestic water service by the District prior to March 14, 1979, shall be exempt from paying Capacity Charges… (3) Agricultural Use… shall be exempt from paying Capacity Charges. (4) New Recycled water meters, including those that are supplied with potable water sources on an interim basis, shall be exempt from paying capacity charges. (5) ADUs converted from existing space and JADU's shall not be considered to be a new residential use and shall be exempt from connection fees or capacity charges.”

EMWD Administrative Code, §5.307(g), p. 329 · source document ↗
Credits and offsets

“If the applicant's property can be served from an inactive service, the applicant shall not be required to pay connection fees. If the applicant requests a change in meter size, additional charges shall be assessed or credits allowed.”

§5.303, p. 324 · source document ↗
How it changes

“Water Financial Participation Charge — Area / Rate as of 1/1/2025 / Rate as of 1/1/2026: General District $7,498/EMS / $7,738/EMS" and "Sewer Financial Participation Charge — Area / Rate as of 1/1/2025 / Rate as of 1/1/2026 / Rate as of 6/17/2026: General District $3,514/EDU / $3,626/EDU / $3,626/EDU" and "Sewer Treatment Plant Capacity Charge — General District $6,662/EDU / $6,876/EDU”

Consolidated Schedule, updated 7/15/2026, pp. 59, 61 · source document ↗

Every published rate

ComponentBasisEffectiveAmount
Water Financial Participation Charge per EDU — $7,738
Recycled Water Supply Development Fee per EDU 1 Jan 2026 $420.00

About these figures

Quoted, not summarized. Every amount and fact on this page is copied from the official document it links to. If we couldn’t find something in a document, we leave it blank instead of guessing.

Before any discounts. Some fees offer credits, waivers or phase-ins. They’re listed above but not subtracted, because whether you qualify depends on your project.

Check the date. Fees change. This page shows what was in force on the date at the top, with a link to the document that set it, so you can confirm the current amount yourself. How all of this is put together.